This bid is for the Pembroke Well 4R Implementation project, which involves decommissioning an existing well and constructing a new well system, including water main installation, process piping, electrical work, and site restoration at the Glenwood Road Water Treatment Plant.
Line Items
ItemQtyUnitEst. Unit PriceEst. TotalCategory
Decommissioning and abandoning existing Well 4 1 lot $50,000.00 $50,000.00 Construction
Installation and commissioning of Town-furnished 75 HP submersible pump, motor, and pitless adapter 1 lot $25,000.00 $25,000.00 Construction
Furnish and install approximately 150 linear feet of 8-inch ductile iron raw water main to Glenwood Road Water Treatment Plant (GRWTP) 150 linear feet $300.00 $45,000.00 Construction
Furnish and install process piping, valves, and one raw water hydrant 1 lot $75,000.00 $75,000.00 Construction
Selective demolition 1 lot $15,000.00 $15,000.00 Construction
Electrical, instrumentation, controls, and SCADA integration work 1 lot $200,000.00 $200,000.00 Construction
Chain link fencing installation 1 lot $10,000.00 $10,000.00 Construction
Paving restoration 1 lot $20,000.00 $20,000.00 Construction
Site restoration 1 lot $30,000.00 $30,000.00 Construction
Incidental work as described in Contract Documents (Well 4R Implementation Project Management and General Conditions) 1 lot $280,000.00 $280,000.00 Construction
Estimated Bid Value$750,000.00

Want the full details?

Sign up free to see the agency name and the original bid posting link, plus contracting-officer contacts and AI response outlines. Every feature is free through December 31, 2026.

Sign Up Free → Already have an account? Log in

Browse More Bids

Bids in MassachusettsGeneral / Other BidsSOLICITATION BidsClosing Soon All Bids