| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| 10" PVC gravity sewer line installation | 770 | linear feet | $150.00 | $115,500.00 | Construction |
| 4" force main installation | 1748 | linear feet | $100.00 | $174,800.00 | Construction |
| Lift station construction and installation | 1 | each | $300,000.00 | $300,000.00 | Construction |
| 16" Jack and Bore steel casing installation | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Manhole installation | 5 | each | $10,000.00 | $50,000.00 | Construction |
| Valve and fitting installation | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Generator installation (for lift station) | 1 | each | $50,000.00 | $50,000.00 | Construction |
| Clearing and grubbing | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Rock removal (if necessary) | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Erosion control items | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Other appurtenances and project completion items | 1 | lot | $120,000.00 | $120,000.00 | Construction |
| Estimated Bid Value | $1,000,000.00 | ||||